Remove asbestos bagging it as its removed from main house and back house.Ref code 3QFQWR
Install 1/2" cdx plywood over entire main house roof and back house using 3" ring shank nails.
Install GAF Stormguard ice and water shield over entire main house roof and back house roof.
Install copper drip edge on all rakes on both roofs
Install 12" x 18" Vermont grey/green slate (approximately 32 squares with waste for both roofs) using 2" copper nails over entire main house roof and back house roof.
Install new terra cotta ridge tiles over all hips and ridges on main house roof and back house roof and point with masonry cement (VCC mix ONLY).
Install new lead boots on all plumbing pipes penetrating roofs, IN EXISTING LOCAITONS
Install ventilation if needed, 750 VENTS NO POWER.
Remove old flat roof,
Install GAF Stormguard on flat roof.
Install GAF 1 iso-board over flat roof using 3" iso-plates and 3" mechanical fastners.
Install GAF 60 mil GRAY TPO (approximately 2 squares with waste) using GAF TPO Bonding adhesive
Install roof edge and GAF TPO cover tape using cover tape adhesive to roof edge.
Note: Trash chutes are required for removal of debris from all roofs
All work must conform to standard VCC policies & guidelines
Permit does not allow for cap flashing on parapets, chimneys or surrounding walls
Torch-applied roofing is not permitted in the Vieux Carré.